High School Track Project

Track Project Starts:

The Renovations and Resurfacing of the Track started on July 21st. The first part was to remove the rubber surface and mill down approximately 1" of old track material. New Hot Top was added last week and the hot top will cure for 21 days and the new rubber surface and painted lines will be installed. I have collected some pictures and video of the project and will update as work progresses.

By Andy Madura

Removing the old rubber and grinding the Hot Top off track

Bob Cat used to remove out track surface on jump pit area


Materials were removed and trucked to a disposal area.

This operation was completed in less then five  [5] hours

Milling Track

Ready for Hot-Top

The Rubber Pellet materials arrived in bags on pallets

The Rubber Track sealant arrives in drums

Nearly a two week process of daily layers being applied

Weather plays a big role,as spraying can only happen when track surface is dry.

You can see the different shades of layers being applied.

Track Project lay down area for products and equipment